NO.
objection
Time
241
Mechanical flow wells monitoring and control in ZaoYuan DaGang oil field(168 Mechanical flow wells monitors and controllers)
2007
240
Mechanical flow wells monitoring and control oil extraction third plant DaGang oil field(114 Mechanical flow wells monitors and controllers)
2006
239
Mechanical flow wells monitoring and control in oil extraction first plant QingHai Oil Field(87+14 mechanical flow wells monitors and controllers)
2006
238
Mechanical flow wells monitoring and control 37 district Sudan
2006
237
Metering Station Automation in Syria
2006
236
NO.2 Natural Gas Liquid Fractionation first oil extraction plant TaHe Oil Field
2006
235
NO.3 apartment control system
2006
234
NO.1 312 Water injection wells monitoring
2006
232
THN1 gas gathering station PLC TaHe oil field
2006
231
312 Water injection wells monitoring TaHe oil field
2006
230
pipeline automation from NO.1 to YAKELA and AT1 PLC and solar cell
2006
229
Solar power supply system in TAHE
2006
228
wellhead automatic control system in methanol plant TUHA
2006
227
wellhead automatic control system of third gas gathering plant CHANGQING
2006
226
automatic control LuoJiazhai ChengDu
2006
225
Automatic control in oil extraction third plant HuaBei Oil Field
2006
224
Gathering processing station DCS system reconstruction SHIXI Oil Field
2006
223
gas injection wells monitoring RTU KENJIYAKE
2006
222
Gathering and Processing DCS system alasi oil field Kazakstan
2006
221
Mechanical flow wells monitoring and control JIDONG Oil Field
2006
220
Mechanical flow wells monitoring and control in Uliyast
2006
219
PLC control system assembling YaKELA XinJiang
2006
218
gathering and transportation control centre Gao Shangbao
2006
217
10-1 metering and pumping station TAHE Oil Field
2006
216
United station LENGHU QingHai
2006
215
Mechanical flow wells monitoring and control in NAISI oil field QingHai
2006
214
wellhead automatic control system in methanol plant XinJiang
2006
213
oil extraction tree RTU TAHE oil field XinJiang
2006
212
Mechanical flow wells monitoring and control ERLIABOLIKE oil field
2006
211
RTU Expansion YAKELA gas field
2006
210
natural gas processing DCS(I/A Series system)Gao Shangbaoo
2006
209
control center Gao Shangbao JiDong oil field
2005
208
Pump station reconstruction JiDong oil field
2005
207
 Mechanical flow wells monitoring and control JiDong oil field
2005
206
G14 oil separator station JiDong oil field
2005
205
flood prevision SCADA DaGang oil field
2005
204
SCADA second oil extraction plant QingHai oil field
2005
203
three-phase measure systemHuaBeioil field
2005
202
Mechanical flow wells monitoring and control oil extraction plant QiuDong
2005
201
DaGang oil field control center simulation
2005
200
DaGang oil field second period
2005
199
NO.1  Wastewater treatment plants expansion
2005
198
live basement energy station DCS TAZHI XinJiang
2005
197
NO.3 Unite station DCS TaHe oil field
2005
196
10district metering station TaHe oil field
2005
195
Unite station DCS NASi Qinghai Oil Field
2005
194
Gas Separator station JinYan YangJahe
2005
193
Pan Steel SiChuan
2005
192
control center WanDongpin
2005
191
metering station QiongLai SiChuan
2005
190
control center heavy Fixing HuiQing HuiCheng
2005
189
gas station control system PinJing ChengDu
2005
188
gas piping SCADA FuHu to TongLin AnHui
2005
187
wellhead BeiJing
2005
186
Water treatment ShangHai
2005
185
water purify system reconstruction TianShan ShangHai
2005
184
Testing system in HUABEI Oil
2005
183
HuaBei NO. 2 Mechanical flow wells monitoring and control
2005
182
NO.21 SCADA  system  ShiNan oil field XinJiang
2005
181
NO.21、31 metering station ShiNan
2005
180
Automation system LuLiang third period
2005
179
Oil separator station DCS NO.31 ShiNan
2005
178
Gas processing station DCS and SCADA NO.7,11 MO
2005
177
Gathering Station DCS ShiNan 31
2005
176
4 Pump station ShiNan 4
2005
175
boiler  control system QianJin XinJiang
2005
174
Gas Separator station control system HeiShan
2005
173
Gas Separator station control system JinLong
2005
172
Gas well control Karamay 82
2005
171
Gas Injection Boiler control JinMA LiaoHe
2005
170
oil convert to coal automation LiaoHe
2005
169
Flood prevent production automation HeKou ShengLi
2005
168
Gathering pump station alarm system ShengLi
2005
167
25Unite station SCADA system ShengLi
2005
166
oil field waste water station HeiYoushan XinJiang
2005
165
wellhead control ShiNan
2005
164
cycle water control RTU HuaChuang DaQing
2005
163
17#、18# Wellhead control ShiNan
2005
162
Waterworks RTU801(Baihong Ltd) FuJian
2004
161
Automation system second Period
2004
160
Mechanical flow wells monitoring and control CaiNan
2004
159
Mechanical flow wells monitoring and control ShiNan
2004
158
well chose control PD101-18 CaiNan
2004
157
Natural Gas Liquid Fractionation automation 5 gas Field HuaAo
2004
156
gathering station DCS ShiNan 21
2004
155
Pump station ShiNan 21
2004
154
Gas Well Control CaiNan XinJiang
2004
153
Gas Separator RTU 42 dis XinJiang
2004
152
Gas gath/Sepa RTU CaiNan
2004
151
Heat supply station 9th dis XinJiang
2004
150
Heat transportation RTU New town karamay
2004
149
metering station control ShiNan 4
2004
148
oil metering station SCADA BaiChong
2004
147
piping line automatic control from ShuGang 2 to ShiHua LiaoHe
2004
146
centre processing boiler automatic control LengYi LiaoHe
2004
145
gas oil processing station DCS system zanaraer hazakestan
2004
144
control center reconstruct ShiXi
2004
143
control center reconstruction CaiNan
2004
142
metering station automation second Oil extraction plant YueJin QinHai
2004
141
oil transportation automation DaGang
2004
140
automation 8th dis TaHe
2004
139
natural gas processing DCS TaHe 2#
2004
138
wastewater treatment RTU TaHe 1#
2004
137
second processing RTU QiuDong
2004
136
automation reconstruction DongHe
2004
135
gas gathering station QiuDong TuHa
2004
134
Gas Separator system QingBaijiang ChengDu SiChuan
2004
133
gas separator system WeiQing, WeiCheng Chengdong SiChuan
2004
132
gas separator system DeZhong to DeXing SiChuan
2004
131
wellhead control HuaChuang DaQing
2004
130
Wellhead control ShiNan 17#、18#
2004
129
Waterworks RTU801(Baihong Ltd) FuJian
2004
128
Pump station ShiNan
2004
127
Water injection third oil extraction plant Petrol China XinJiang
2004
126
Polyester production RTU HuaXian LTD ZheJiang
2004
125
Water injection third oil extraction plant Petrol China XinJiang
2004
124
Waterworks Automation Buerji        
2004
123
wastewater treatment automatic control system ShiHezi                          
2004
122
wellhead control Urumuqi weststation           
2004
121
wellhead control HuaChuang DaQing
2004
120
Wastewater treatment TaHe1#
2004
119
Pump station ShiNan
2004
118
power station and water injection RTU XingGuang LTD
ShaoXing  
2003
117
花山站Automation HuaShan station QingHai
2003
116
station control Auxs ChengDu
2003
115
Gas station SCADA DaLian
2003
114
metering cable RTU WanDong ChengDu
2003
113
mixing transportation system automation ShiNan XinJiang
2003
112
power station and water injection RTU XingGuang LTD
ShaoXing  
2003
111
auto metering instruments LiaoHE
2003
110
gas metering system of gas separator station GongJin ChengDu
2003
109
Mechanical flow wells monitoring and control RTU DIWEIR
2003
108
metering station reconstruction First oil extraction Plant QingHai
2003
107
5# gas injection station and oil processing station RTU BaiChongQI
2003
106
heat supply gas injection RTU 5#、20# KeQian
2003
105
Metering stationTaHe9
2003
104
Oil storage station RTU 3# DaQing
2003
103
SCADA system QiuLing oil extraction plant TuHa
2003
102
Oil Processing Station DCS BaiKouQuan
2003
101
Office Building RTU XinJiang
2003
100
Gas Field automation system Expansion QiuDong
2003
99
Natural gas metering system BaXian QingHai
2003
98
Gas well Control PengWu District
2003
97
natural gas auto metering system ChongQin Petrol China XiNan
2003
96
Oil processing DCS 81# XinJiang
2003
95
Natural Gas Processing DCS CaiNan
2003
94
oil extraction control center system reconstruction KeJIYake
2003
93
Boiler automation second oil extraction plant QinHai
2003
92
metering gas injection station KejiYake
2003
91
18#,19# Heat supply RTU KeQianShi dixtrict
2003
90
metering and separator station 6# TaHe
2003
89
RTU/RPC ErLianBaoLiGe
2003
88
30*104t/a energy station automation  HuaTuGou
2003
87
盆五5井区information transform PengWu district
2003
86
metering station JiangSu
2003
85
gas processing station automation ZhaNaRuoer Hazakestan
2003
84
oil field gas metering and separator station KeYaKe Hazakestan
2003
83
boiler automation HunLun XinJiang
2003
82
SCADA in PengWu
2003
81
gas metering station ZhuJiaQiao
2003
80
automation system reconstruction CaiNan
2003
79
Mechanical flow wells monitoring and control  Anla mountain
2003
78
wellhead control TuLuFan Power Plant
2003
77
SCADA second waterworks YuMen
2003
76
wellhead control LuJiu XinJiang
2003
75
Wastewater treatment automation First oil extraction plant Changqin
2003
74
wastewater treatment automation ShiNan
2003
73
water injection station RTU and wellhead control
2003
72
wastewater and heat supply automation third oil extraction plant XinJiang
2003
71
149 waterworks RTU and gathering /separator station PengWu XinJiang
2003
70
wastewater treatment automation BoLe
2002
69
metering station RTU LeShan
2002
68
Gas separator metering system NiLuo SiChuan 
2002
67
Unite station DCS MoBei XinJiang 
2002
66
Boiler DCS HongShan XinJiang
2002
65
Boiler RTU HongLian Station First oil extraction Plant XinJiang
2002
64
Humidity Control XiBeiYuan  
2002
63
Compressor station RTU XiaZi street Gas Separator/transportation LTD
2002
62
Second SCADA HuaBei Oil Field
2002
61
metering station RTU FuNiu ChuanNan ShuNan
2002
60
SCADA in second metering station Gas Field QingHai
2002
59
Mechanical flow wells monitoring and control TaHe
2002
58
Unite station TaHe
2002
57
11# metering station automation QingHai
2002
56
Metering system Gas Field ChongQin
2002
55
S-58 metering station automation QingHai
2002
54
gas Transport piping DCS from TaHe to LunTai
2002
53
SCADA system China Refine TianJin
2002
52
27# metering station QinHai
2002
51
Humidity control ZuanCaiYuan LiaoHe
2002
50
SCADA System LuLiang Oil Field
2002
49
automation testing ShengQuan TuLuFan TuHa
2002
48
metering station RTU FuNiu ChuanNan ShuNan
2002
47
Boiler DCS reconstruction NanQuan
2002
46
10# metering station QingHai
2002
45
LuLiang center oil processing automation second period
2002
44
metering station RTU CaiNan
2002
43
SCADA system second oil extraction QingHai
2002
42
SCADA system MoBei
2002
41
Mechanical flow wells monitoring and control MoBei
2002
40
Mixing transport testing automation ShiNan
2001 -2002
39
SCADA system Forth oil extraction plant HuaBei
2002
38
SCADA system ErLian Oil extraction plant HuaBei
2002
37
10# metering station SCADA system second oil extraction plant QingHai
2002
36
Gas processing station DCS MoBei
2000 -2002
35
1-4# heat supply station SCADA system 7# district BaiChong
2002
34
109# Heat supply SCADA system KeQian
2002
33
Oil Processing station DCS third oil extraction XinJiang
2002
32
DuShanZi-703 Piping line SCADA
2002
31
Natural gas piping line automation from ShiQiao to DuZhou
2002
30
Boiler DCS HuanXil